Carlton Academy Trust (CAT) were seeking a way to significantly cut long-term energy costs and accelerate their progress towards net zero ahead of the UK’s 2050 target. With multiple schools across the Trust, they required a solution that would deliver meaningful carbon savings while avoiding upfront capital costs.
6
Weeks Installation Time
160,354
kg Of Carbon Saved Annually
800,918
kWh Annual Energy Generation
1.5m
£’s Saved Over 25 Years
Project Details
Carlton Academy Trust
Shawton Energy developed and delivered a 25-year portfolio PPA covering 7 sites, totalling 817 kWp. The project was fully developed in-house and received Department for Education (DfE) consent, setting a benchmark for how the public sector can utilise PPAs to meet decarbonisation goals.
During the summer 2025 break, Shawton successfully installed 313 kWp across 6 Carlton Academy Trust sites, enabling a rapid rollout with minimal disruption to staff and students.
Solar PV rollout across 7 sites
Minimal disruption during installation process
Efficient delivery within 6 weeks
Methodology & Implementation
01 Efficient Delivery
All installations completed in just 6 weeks.
02 Stakeholder Coordination
Close collaboration with the Department for Education to ensure a smooth approvals process.
03 Multi-Site Rollout
Solar PV successfully deployed across the Trust’s schools as part of a wider portfolio plan.
04 Minimal Disruption
Scheduling around term times to avoid impact on teaching and learning.
Could your business benefit from solar energy?
The Result
The project has delivered significant cost and carbon savings across the trust:
- 800,918 kWh of renewable electricity generated annually
- 160,354 kg of CO₂ emissions saved every year
- Over £1.5m in projected savings over 25 years
- No upfront cost thanks to Shawton’s PPA model